|
Site Utility
Communications
Environmental
Completed Projects
Team Leaders
Trenchless Technology
Hourly Services
|
Environmental Project Summary
Project:
Terracon
Fuel System - Remediation
Owner/Client:
Terracon
2211 So. 156th Circle
Omaha, NE 68130
Rod Baumann
(402) 330-2202
Type of Waste / Contaminant:
Former Feagin's Service Station
Ong, Nebraska
Description of Work:
Remediation and excavation tasks to former service and gas station.
Method of Construction:
This project consisted of removing contaminated soils by excavating and hauling materials. A filter pack, 18' deep, was used as a vapor barrier with soil venting tubes and vacuum attachment to remove the vapors. The area was then backfilled and filled with concrete.
|