FEATURED PROJECT...
BryanLGH West - Sanitary Sewer Tap Repair
Lincoln, NE - It is an age old question, which came first, the pipe or the building? In the case of an addition to the BryanLGH West Medical Center, the pipe came first. Sampson Construction was hired by BryanLGH to fix a faulty sewer tap at their west location near 16th and South Street. It sounds simple enough, Sampson Construction subcontracts the below grade work to General Excavating to expose the faulty tap, repair it, and restore the site. However, time and the activities of humans have a tendency to complicate things. The original City of Lincoln sewer main was located approximately 15-feet deep. A good sized hole would need to be dug to be sure but again, nothing too difficult. The real problem was as the BryanLGH West Campus expanded over the years, an addition was built over the city sewer main. To complicate the matter further, when the addition was constructed, an additional 15-feet of fill was added to the site. The scope of the project now becomes fixing a faulty sewer tap located 30-feet under an addition that houses a sensitive area of the medical center.
General Excavating has built a reputation for successfully tackling difficult jobs that other utility contractors typically avoid. This particular sanitary sewer repair project presented General Excavating an opportunity to showcase their "tough job" abilities. The challenge, how to excavate a hole 30-feet deep and remove the spoil under an existing nurses' station, while maintaining a safe and clean work environment? More than one option was considered but the plan agreed upon by General Excavating, Sampson Construction, and BryanLGH included using a tunnel liner plate system to reach the faulty tap. First, the nurses' station was relocated and the surface concrete removed. Using the tunnel liner system, as a hole is dug, a ring-shaped protective system is installed. As the excavation gets deeper another ring section of the tunnel plate liner system is bolted on to the bottom. In this particular excavation, the plates slid down as the hole was dug making it easier to attach new rings to the top. In this way, workers were protected from cave-ins as they continued the excavation down to the faulty tap.
The next hurdle to overcome was how to reach a sanitary sewer pipe 30-feet deep without using an excavator? The answer, have Tan Aire use a high pressure water wand to loosen the soil and a powerful vacuum truck to remove the spoil. Two hundred-feet of piping was connected to the vacuum truck parked outside the medical center. Scaffolding was installed in the hallway of the hospital to support the eight-inch slurry removal pipe and another four-inch casing pipe which housed the water supply used to power the wand. Using vacuum excavation and the tunnel liner plate system, approximately 4-feet a day was achieved. Once the faulty pipe was reached, Mechanical Western removed and replaced the tap and a concrete base was poured for support. The four-inch casing pipe was used as a conduit to bring sand in used for backfilling the excavation. A riser pipe was added and Sampson Construction restored the surface concrete. The rings of the tunnel liner plate system were left in place.
"All involved were pleased with the project," according to General Excavating's project manager, Brian Egr. "There was a great deal of planning involved on everything from air monitoring of a confined space to getting guys up and down a deep shaft. There was no room for a ladder, so we used an electric chair. Sampson was great to work with and it really was a case where everything, despite the difficulties, went according to plan."
Back to Top of Page
Landscape Supply Website
Check out our new landscape supply website. A fresh new look for 2009 to make planning your projects from home easy with our online product pictures, updated price lists, project how to's, inspiration gallery and a materials calculator. Want to be the first to know about sales and events? Sign up for our e-newsletters at www.gelandscapesupply.com
Back to Top of Page
Above & Beyond
INSPIRING THE NEXT GENERATION
Dan Nelson took time out of his day to participate in the 21st annual Construction Fair hosted recently at Lincoln Northeast High School. Lincoln Public Schools and the Cornhusker Chapter of Associated Builders and Contractors have joined efforts to give area youth a chance to learn more about the construction industry and careers available. Dan has worked at General Excavating for over two decades and has participated in the Construction Fair many times over the years.
Back to Top of Page
QUEST
FOR KNOWLEDGE
The employees at General Excavating have been working hard to improve their craft over the past couple of months. Continued education and ongoing training equals better service for our clients. Congratulations to the following individuals who worked to improve their level of knowledge and skill in the underground construction business.
Successfully completed COMPETENT PERSON TRAINING; Tanner Hanson, Larry Corter, John Kremlacek, Francisco Cuevas, Jon Bounds, Brian Egr, Robert Feliciano, Chris Boeck, Aaron Jeffers, Cody Cassler, Matt Flynn, Joe Johnson, Jake Schweitzer, Josh Weatherly.
Successfully completed 8-hour HAZARDOUS WASTE & EMERGENCY RESPONSE OPERATIONS TRAINING refresher course; Ken Imig, Leon Bergfield, Jim Oldfield, Steve Crosby, Steve Stowers, Rich Roberts, Randy McDonald.
Did You Know?
General Excavating recently attained a "SILVER" level safety designation from the Association of Builders and Contractors. The award recognizes those contractors who maintain a high-level safety program, promote safe work practices, and emphasize ongoing education and training.
Back to Top of Page
YOUR UNDERGROUND PARTNER
Project Briefs...Completed & Ongoing Projects
Project
- South Street Rehabilitation
- Lincoln, NE
Owner
- Black Hills Energy
Sub-Contracted to
- Black Hills Energy
Scope
- Horizontal bored 4" plastic gas line as part of a rehabilitation project along South Street to replace an aging steel gas line.
Project
- UNL Whittier Building Renovation
- Lincoln, NE
Owner
- University of Nebraska
Sub-Contracted to
- H & S Plumbing and Heating, Co.
Scope
- Constructed the site utilities including water, storm, and sanitary sewer.
Project
- Star Tran Bus Barn Remediation
- Lincoln, NE
Owner
- City of Lincoln
Sub-Contracted to
- HWS Consulting Group, Inc.
Scope
- Installed a vacuum remediation system to recover diesel fuel, horizontal bored an extraction line, and restored the site.
Project
- Sanitary Sewer Relocation
- Nebraska City, NE
Owner
- Walgreens
Engineer
- Olsson Associates
Scope
- Rerouted approximately 260-feet of 8-inch sewer, set manholes, and appurtenant work.
Back to Top of Page
TRADITION OF CONSTRUCTION EXCELLENCE
General Excavating was recognized for outstanding performance in the construction industry by the Associated Builders and Contractors at their Excellence in Construction Awards Banquet held earlier this year. General Excavating's work on Stevens Creek Capital Improvement Projects #3 & #4 for the City of Lincoln and the Lower Platte South Natural Resources District is the latest example of construction excellence. Since 1996 General Excavating has been honored seven times on a wide range of infrastucture and public works construction projects. Past winners include: 1996 Antelope Commons Dam & Control Structures - Lincoln, NE 1997 Memorial Stadium Sanitary Sewer Upgrade - Lincoln, NE 1999 Excel Corporation Demolition & Remodel - Schuyler, NE 2003 Calamus Fish Hatchery Drainage Modifications - Burwell, NE 2003 Salt Valley Generating Station Supply & Return Pipeline - Lincoln, NE 2004 Henry Doorly Zoo Gorilla Valley Complex - Omaha, NE 2005 Deadman's Run Channel Maintenance - Lincoln, NE |
Back to Top of Page
Photo of the Quarter
An opportunity for General Excavating's employees to show others the work they perform. Winner's receive cash and have their photo displayed at General Excavating. Steve Stowers or "Okie" as he is known to most of us submitted this quarter's winning photograph. A project foreman, Okie has worked at General Excavating for nearly 11 years. Okie and his crews complete environmental construction and fuel tank installation projects for a large number of clients throughout the Midwest. General Excavating, working for Burlington Northern Santa Fe Railway, cleaned-up a coal spill near Aurora, Nebraska. The coal was vacuumed, loaded into trucks, and hauled to a landfill for disposal. |
Back to Top of Page
Please email address changes, inquiries, and requests for more newsletters to rmcdonald@generalexcavating.com


