HomeAbout UsDiversified Services Landscaping NewsCareersLinksContact Us
GE Header
NEWSLETTERS:

Spring 2008
Winter 2007
Summer 2007
Spring 2007

Fall 2006
Summer 2006
Spring 2006

Fall 2005
Summer 2005
Winter 2005

Winter 2004
Spring 2004
Summer 2004

Winter 2003
Spring 2003
Summer 2003
Fall 2003

Winter 2002
Spring 2002

Spring 2001
Summer 2001
Fall 2001

Winter 2000
Spring 2000
Summer 2000
Fall 2000

Winter 1999
Spring 1999
Summer 1999
Fall 1999

Press Releases

FEATURED PROJECT...

Secondary Containment & Fuel Piping Improvements

Installation of an 80-foot section of PermaAlert Ultra Steel fuel supply piping.

Excavation through the earthen protective dike and asphalt parking lot.

LES Rokeby Generating Station - General Excavating has built a reputation of excellence by specializing in unique below grade construction projects. While the Secondary Containment and Fuel Piping Improvement Project included a great deal of below grade work, it was the challenges above ground that required the most attention. Heavy rainfall, manufacturer delays, a unique pipe project, and a compressed schedule all played a part in pushing General Excavating and their subcontractors to find ways to overcome challenges on this Lincoln Electric System improvement project.

Following the design of Olsson Associates, work commenced with the enlargement of the containment cell. However, soon after the start of construction heavy rainfall left four to eight inches of water in the basin. Scrapers were unable to remove the mud and vegetation on their own so the muck was pushed into piles and loaded into the scrapers with an excavator. The LES Rokeby Generating Station located on the outskirts of Lincoln is the primary peaking power station for the Lincoln Electric System. EPA requirements dictated enlargement of the existing containment cell in the event of a rupture or failure of a 5 million gallon fuel oil storage tank. If General Excavating failed to meet the schedule deadlines, the power station would be unable to comply with EPA regulations and begin its operation of storing fuel oil.

Excavation of the secondary containment system at the LES Rokeby Generating Station.

Another main component of this project included abandoning an existing fuel oil line with flowable fill and installing new double-walled steel pipe protected by an outer layer of fiberglass. The new PermaAlert Ultra steel pipe required a great deal of labor for successful installation. The 40' pipe was first air tested, then welded together by Nifco Mechanical for installation of eighty-foot sections into the trench. The new joints were hand wrapped with fiberglass in the ditch. The pipe also possessed a leak detection system that would alert the owner in case of future leaks. The abandoned fuel oil supply pipe that criss-crossed the proposed construction route hampered excavation for the new fuel oil supply pipelines. Communications, other existing utilities, a chain link fence, asphalt parking lot, as well as a retaining wall stood in the way of construction of the new piping.

General Excavating was able to meet the demands of the job allowing the LES Rokeby Generating Station to continue its normal operation without disruptions. The success on this project was due in large part to the well-qualified subcontractors collaborating on this project. An EPA approved containment system as well as new double walled steel pipe with leak detection is now in place to address the needs of the LES Rokeby Generating Station and their capacity to provide power to the residents of Lincoln.

Back to Top of Page

Did You Know?

Duain Colburn, Mark Abbott, Randy McDonald, and Rich Roberts recently completed their OSHA 40-Hour HAZWOPER training. As part of General Excavating's Environmental Division, Duain, Mark, and Rich will construct remediation systems and complete HAZMAT clean-up projects for clients throughout the Midwest.

Back to Top of Page

Above & Beyond

“This project was especially challenging and demanding due to the very short construction schedule.”

  • James Burroughs, PE
  • Olsson Associates

Back to Top of Page

The Pipeline

FIBERGLASS…

General Excavating proposed and the City of Lincoln approved and accepted the use of fiberglass manholes on the Waterford Estates Trunk Sewer Project. This is a first in the City of Lincoln.

ROAD TRIP…

GE Landscape Supply invited nearly 30 landscaping contractors to join them for a trip to Kansas City to attend the Western Landscape Show.

CERTIFIED…

Jim Brunner, project manager at General Excavating, received his license from the State of Nebraska as a certified Pump Installation Contractor.

STORM SEWER…

RCP or HDPE What fits your project? Visit with GE's project managers to find out what will work best on your upcoming project.

AWARDED…

The Lower Platte South Natural Resources District awarded the Stevens Creek Capital Improvement Project #3 & #4 to General Excavating.

Back to Top of Page

YOUR UNDERGROUND PARTNER

Project Briefs... Completed & Ongoing Projects

Project

  • Humboldt Downtown Renovation
  • Humboldt, NE

Owner

  • City of Humboldt

Engineer

  • Gilmore & Associates, Inc.

Scope

  • Renovation of eight downtown blocks including storm sewer, sanitary sewer, water mains and associated work.

Project

  • LES-DES Phase 2 Distribution Piping
  • Lincoln, NE

Owner

  • District Energy Corporation

Engineer

  • Farris Engineering, Inc.

Scope

  • Construction of distribution piping to the Court House Plaza and 900 J Building and associated work.

Project

  • Oak Creek Basin Trunk Sewer
  • Lincoln, NE

Owner

  • City of Lincoln

Engineer

  • HDR Engineering, Inc.

Scope

  • Installation of over 3,000 lineal feet of 42-inch sanitary sewer including the construction of a twelve-inch siphon under Oak Creek.

Project

  • Underground Storage Tank Installation
  • Crete, NE

Owner

  • Bunge North America

Engineer

  • Bunge Milling, Inc.

Scope

  • Removal of a concrete lid and installation of a 15,000-gallon fiberglass tank and associated work.

Back to Top of Page

Thank You

Since 1987 General Excavating has been YOUR "UNDERGROUND" PARTNER. We have enjoyed working with many of the same clients over the years and look forward to 2008 as the first of twenty more years of providing you underground solutions.

Thanks also to the following employees who are celebrating important milestones in their career at General Excavating. The quality of a company is only as good as the people who work there and we have been blessed with terrific employees over the past twenty years.

  • MIKE STEWART 20 Years
  • YANCEY KEISER 15 Years
  • DAVE WATERS 15 Years
  • DAN HOLLEY 10 Years
  • STEVE CROSBY 10 Years
  • LONNIE BULLOCK 5 Years
  • FRANCISCO CUEVAS 5 Years
  • DAVE MICHAELSON 5 Years
  • BRIAN EGR 5 Years
  • ROY HOWARD 5 Years

Back to Top of Page

Photo of the Quarter

hitting the target

An opportunity for General Excavating's employees to show others the work they perform. Winner's receive cash and have their photo displayed at General Excavating.

Dale Hanson submitted this quarter's winning photograph. A project foreman, Dale has worked at General Excavating for nearly 3 years. Dale completes a wide range of water, sanitary sewer, and storm sewer projects for private and public owners throughout the area.

General Excavating, working for Nestle Purina Petcare Company, constructed drainage improvements at the Nestle Purina plant in Crete, Nebraska. The photograph illustrates the excavation seen through the 72" corrugated metal pipe prior to its installation.

Back to Top of Page

Please email address changes, inquiries, and requests for more newsletters to rmcdonald@generalexcavating.com

Back to Top of Page