Project:
City of Valley (Spring 2002)
Description of Work:
The City of Valley wanted to eliminate an extensive flooding problem
they encountered each time it rained. General Excavating was hired to
install a drainage and pumping system to alleviate the problem. Over 1200
feet of force main, 1700 feet of storm sewer pipe and a 25-foot deep wet
well were installed. The Engineer was Olmsted & Perry Consulting Engineers.
|