Site Utility Project Summary
Project:
New Sewer Line ‚ Pace Boning
Owner/Client:
Excel Corporation
590 County Road 9
Schuyler, NE 68661
E. V. Pence, Capital Manager
(316) 291-2500
General Contractor: Ayars & Ayars, Inc.
6500 Holdrege
Lincoln, NE 68505
Matt Biggs, Project Manager
(402) 435-8600
Location:
Schuyler, Nebraska
Description of Work:
This project consisted of excavation for sewer lines, installation of sewer and manholes, as well as removal of concrete and new walls for partitions. All excavation was 100% sand and had to be removed through a double walk-in-door.
Method of Construction:
Construction methods included open cut by mini excavator and skid loaders only. All work was completed at night and over holidays to meet their critical timeline. |