Site Utility Project Summary

Kawasaki Project:
Kawasaki Railcar Manufacturing Facility

Owner/Client:
Kawasaki Corporation
6600 NW 27th Street
Lincoln, NE 68521
Larry Younger, Construction Manager
(402) 476-6600

Subcontractor to:
Nifco Mechanical
Willmar Electric Service
Shanahan Mechanical & Electrical

Location:
Northwest Lincoln, Nebraska

Description of Work:
Construction of 6,000-feet of water main, 8,000-feet of storm sewer pipe, 3,600-feet of sanitary sewer pipe and 2,000-feet of electrical duct bank.

Method of Construction:
The project was on a tight time schedule with several contractors working on the site at the same time. Standard trenching and backfilling was used on this project.